A Revolution in Energy Production
A Community Hydro Electric Scheme for Settle
Planning permission granted Feb 2009
Abstraction Licence granted Feb 2009
Construction of the Hydro Scheme by the contractors, Lakeland Marine Construction began on Monday 15th June. It is scheduled to complete by October and Settle Hydro Ltd will be generating electricity by November 2009.